A contractor receives three subcontractor bids for HVAC: $18,000, $21,500, and $31,000. What is the BEST practice when selecting a bid to include in the prime estimate?
-
A
Always use the lowest bid
-
B
Evaluate all bids for scope completeness before selecting
-
C
Average the three bids for a balanced estimate
-
D
Use the middle bid to avoid risk