A contractor uses the 'square foot method' for a preliminary cost estimate. What is the PRIMARY limitation of this approach?
-
A
It cannot be used for residential projects
-
B
It ignores local labor and material cost variations
-
C
It requires completed architectural drawings
-
D
It overestimates material waste factors