A subcontractor fails to meet a project milestone, causing a 10-day delay. The general contractor incurs additional supervision costs. What type of damages would the GC likely seek?
-
A
Liquidated damages
-
B
Consequential damages
-
C
Punitive damages
-
D
Nominal damages