A residential contractor is developing a project schedule using the Critical Path Method (CPM). Which task characteristic defines a critical path activity?
-
A
It has the highest cost among all tasks
-
B
It has zero total float
-
C
It requires specialized subcontractors
-
D
It is the first task to be completed