A homeowner requests a verbal change order to add a deck during construction. What is the contractor's best practice?
-
A
Proceed immediately to maintain client satisfaction
-
B
Document the change in a written change order signed by both parties before starting work
-
C
Add the work and include it in the final invoice
-
D
Refuse the request until the original contract is complete