Project Planning & Scheduling Flashcards
7 cards from real CRC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Planning & Scheduling flashcards as text
A homeowner wants to reduce the project timeline by starting interior framing before the foundation concrete has fully cured. This is an example of:
Answer: Fast-tracking
Fast-tracking overlaps activities that would normally be done in sequence, reducing duration but increasing risk.
Which planning tool is most effective for identifying potential risks before a residential project begins?
Answer: Pre-construction risk register
A risk register identifies, analyzes, and documents potential risks and planned responses before construction starts.
A construction schedule shows Activity B has a Start-to-Start (SS) relationship with Activity A with a 5-day lag. This means:
Answer: B cannot start until 5 days after A starts
A Start-to-Start with 5-day lag means Activity B cannot begin until 5 days after Activity A has started.
When sequencing residential construction activities, which of the following is a mandatory dependency?
Answer: Pouring concrete footings before erecting framing
Footings must be poured and cured before framing can be erected — this is a physical (mandatory) dependency that cannot be changed.
A project manager uses the '80/20 rule' during schedule monitoring. What does this mean in a construction context?
Answer: 80% of schedule problems are caused by 20% of activities or subcontractors
The Pareto principle (80/20 rule) suggests that most schedule problems stem from a small number of recurring root causes or parties.
Which contract document takes precedence when there is a conflict between the specifications and the drawings?
Answer: The order of precedence clause in the contract governs which document controls
The contract's order of precedence clause defines which document governs in case of conflicts between drawings and specifications.
A contractor is planning a custom home and needs to order long-lead items such as custom windows. Which scheduling step ensures these items arrive on time?
Answer: Back-calculating from the installation date to determine order deadlines
Back-scheduling from the required installation date determines the latest allowable order date to prevent long-lead items from delaying the project.