  1. Which scheduling technique uses arrows to represent activities and nodes to represent events?

    Answer: Arrow Diagramming Method (ADM)

    Arrow Diagramming Method (ADM) uses arrows for activities and nodes for events, also called Activity-on-Arrow (AOA).

  2. A residential contractor discovers soil conditions require deeper footings than planned. Which document should be issued first?

    Answer: Change order

    A change order formally documents and authorizes scope, cost, and schedule changes when unforeseen conditions alter the original plan.

  3. What is the primary purpose of a baseline schedule in residential construction?

    Answer: To serve as the original approved plan against which progress is measured

    The baseline schedule is the approved original plan used to measure project performance and identify variances.

  4. A homeowner requests an addition that was not in the original contract. How should a contractor handle this?

    Answer: Issue a written change order before starting work

    A written change order must be executed before additional work begins to protect both the contractor and owner legally and financially.

  5. In a Gantt chart, what do overlapping bars typically indicate?

    Answer: Activities occurring simultaneously (parallel work)

    Overlapping bars on a Gantt chart show that two or more tasks are scheduled to occur at the same time.

  6. Which resource leveling strategy extends the project duration to avoid resource conflicts?

    Answer: Resource leveling

    Resource leveling adjusts the schedule, often extending the end date, to resolve over-allocation of resources.

  7. A framing crew finishes 3 days early. Which scheduling concept describes the time saved that can benefit successor tasks?

    Answer: Free float

    Free float is the amount of time an activity can be delayed without delaying its immediate successor activities.