A principal investigator requests to move $15,000 from personnel to equipment mid-project. Under Uniform Guidance, when is prior approval from the federal agency required for this rebudgeting?
-
A
When the reallocation exceeds 10% of the total award
-
B
When the reallocation exceeds 25% of the total award
-
C
Prior approval is always required for any personnel-to-equipment transfer
-
D
Prior approval is never required if the PI approves