A remodeler discovers a subcontractor has abandoned the job mid-project. The FIRST step should be:
-
A
Immediately hire a replacement without documentation
-
B
Issue a written cure notice or notice of default per the subcontract terms
-
C
Withhold all further payments and say nothing
-
D
Report the sub to the licensing board before contacting them