During construction of a public water main replacement, an unforeseen archaeological site is discovered. What is the FIRST action the project manager should take?
-
A
Continue work and document the finding in the project log
-
B
Stop work in the affected area and notify the appropriate regulatory authorities
-
C
Photograph the site and resume work to avoid schedule delays
-
D
Issue a change order to remove the archaeological material