In a public works capital improvement program (CIP), which criterion is MOST important when prioritizing projects for funding?
-
A
Projects with the lowest cost should be funded first
-
B
Projects should be evaluated against community need, safety, regulatory compliance, and lifecycle cost
-
C
Projects requested most recently should receive priority
-
D
Projects with available grant funding should always be ranked first