What is the primary purpose of a pre-bid conference in public works procurement?
Select your answer
A
To allow agency staff to preview contractor qualifications before bidding opens
B
To provide all potential bidders equal access to clarifications about the project and specifications
C
To negotiate pricing with the most qualified contractors before bids are submitted
D
To allow contractors to inspect competitors' past project performance