A performance improvement project is running 15% over budget at the midpoint. Which metric from earned value management best describes this situation?
-
A
Schedule Performance Index (SPI) below 1.0
-
B
Cost Performance Index (CPI) below 1.0
-
C
Cost Variance (CV) above zero
-
D
Schedule Variance (SV) below zero