CPT CPT Production Planning & Scheduling 4 — Questions and Answers
Question 1: A production scheduler notices that a machine has been down for 4 hours unexpectedly. Which metric is most directly impacted?
- Overall Equipment Effectiveness (OEE) (Correct answer)
- Mean Time Between Failures (MTBF)
- Takt time
- First pass yield
Correct answer: Overall Equipment Effectiveness (OEE)
OEE measures availability, performance, and quality, so unplanned downtime directly reduces the availability component of OEE.
Question 2: In a pull-based production system, work orders are released based on:
- A fixed schedule created weeks in advance
- Signals from downstream consumption or demand (Correct answer)
- The capacity of the first operation
- Forecasted demand from marketing
Correct answer: Signals from downstream consumption or demand
Pull systems release production work only when downstream processes signal a need, preventing overproduction.
Question 3: Which scheduling technique assigns jobs to machines by processing the shortest job first?
- First In First Out (FIFO)
- Shortest Processing Time (SPT) (Correct answer)
- Longest Processing Time (LPT)
- Critical Ratio (CR)
Correct answer: Shortest Processing Time (SPT)
SPT prioritizes the job with the least processing time, minimizing average flow time and work-in-process.
Question 4: A plant produces 500 units per 8-hour shift. The takt time is 1 minute per unit. If a bottleneck station can only produce 420 units per shift, what is the best immediate action?
- Increase the shift length to 10 hours
- Add overtime or a second operator at the bottleneck (Correct answer)
- Reduce the production target to 420 units
- Increase inventory buffers before the bottleneck
Correct answer: Add overtime or a second operator at the bottleneck
Adding capacity at the bottleneck directly addresses the constraint limiting throughput to below customer takt requirements.
Question 5: What does a Gantt chart primarily display in a production scheduling context?
- Inventory levels over time
- The sequence and timing of jobs across resources (Correct answer)
- Quality defect rates by shift
- Cost per unit by product line
Correct answer: The sequence and timing of jobs across resources
A Gantt chart shows tasks or jobs plotted against a time axis, illustrating when each job runs on each resource.
Question 6: When calculating net requirements in MRP, which formula is correct?
- Net Requirements = Gross Requirements + Scheduled Receipts + On-Hand Inventory
- Net Requirements = Gross Requirements − On-Hand Inventory − Scheduled Receipts (Correct answer)
- Net Requirements = Gross Requirements × Safety Stock Factor
- Net Requirements = On-Hand Inventory − Gross Requirements
Correct answer: Net Requirements = Gross Requirements − On-Hand Inventory − Scheduled Receipts
MRP subtracts available inventory (on-hand plus scheduled receipts) from gross requirements to determine what still needs to be produced or ordered.
Question 7: A company changes from monthly to weekly production planning cycles. Which benefit is most likely?
- Lower planning labor costs
- Faster response to demand changes (Correct answer)
- Reduced machine setup frequency
- Higher batch sizes per run
Correct answer: Faster response to demand changes
Shorter planning cycles allow the schedule to be updated more frequently, enabling quicker reactions to changes in customer demand or supply disruptions.
A production scheduler notices that a machine has been down for 4 hours unexpectedly.
Which metric is most directly impacted?