CPT Production Planning & Scheduling Flashcards

7 cards from real CPT practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 CPT Production Planning & Scheduling flashcards as text
  1. Which production planning document authorizes the shop floor to begin manufacturing a specific quantity of a part?

    Answer: Work Order (WO)

    A work order is the formal authorization document that triggers shop floor activity for a defined quantity and due date.

  2. In finite capacity scheduling, what happens when a machine's available capacity is exceeded?

    Answer: Jobs are rescheduled or rerouted to stay within capacity limits

    Finite capacity scheduling respects real capacity limits and adjusts job timing or routing rather than overloading a resource.

  3. Safety stock is primarily used to protect against:

    Answer: Variability in demand and supply lead time

    Safety stock acts as a buffer inventory to absorb unexpected fluctuations in customer demand or supplier delivery variability.

  4. A production planner uses the Critical Ratio (CR) to prioritize jobs. A job with a CR less than 1.0 indicates:

    Answer: The job is behind schedule and needs expediting

    A critical ratio below 1.0 means time remaining is less than the work remaining, signaling the job is late or at risk of being late.

  5. Which of the following best describes a mixed-model production schedule?

    Answer: Interleaving different product variants in a sequence to level demand

    Mixed-model scheduling sequences different variants throughout the day to level workload, reduce batch sizes, and match actual customer demand patterns.

  6. Capacity Requirements Planning (CRP) is performed after MRP to:

    Answer: Verify that planned work orders can be completed within available machine and labor capacity

    CRP translates MRP-generated work orders into capacity loads and compares them against available capacity to identify overloads or underloads.

  7. A planner observes that actual cycle time consistently exceeds standard cycle time on one workstation. The most appropriate first step is to:

    Answer: Investigate the root cause of the cycle time variance

    Root cause analysis should precede any corrective action to ensure the solution addresses the actual problem rather than masking it.