CPT CPT Production Planning & Scheduling 2 โ Questions and Answers
Question 1: What is a 'bottleneck' in a production process?
- A storage area for finished goods
- The operation that limits overall throughput (Correct answer)
- A type of assembly fixture
- An employee safety hazard
Correct answer: The operation that limits overall throughput
A bottleneck is the slowest operation in a process; it constrains the output rate of the entire production line.
Question 2: Which term describes the planned quantity of product to be produced in a specific time period?
- Safety stock
- Production quota (Correct answer)
- Lead time
- Takt time
Correct answer: Production quota
A production quota is the target output quantity assigned for a given shift, day, or week.
Question 3: Takt time is calculated by dividing:
- Machine hours by number of products
- Available production time by customer demand rate (Correct answer)
- Labor cost by unit output
- Cycle time by number of operators
Correct answer: Available production time by customer demand rate
Takt time = available production time รท customer demand; it sets the pace at which products must be completed.
Question 4: Which document communicates the quantity of a product to be built and its due date to the shop floor?
- Safety data sheet
- Work order / job ticket (Correct answer)
- Material safety sheet
- Calibration record
Correct answer: Work order / job ticket
A work order (job ticket) authorizes production of a specific quantity by a specific date and travels with the job on the floor.
Question 5: What is 'lead time' in a manufacturing environment?
- The time required for a supervisor to approve overtime
- The total time from order release to completion of a part or product (Correct answer)
- The delay caused by equipment breakdown
- The interval between quality inspections
Correct answer: The total time from order release to completion of a part or product
Lead time is the total elapsed time required to produce an item, from the release of a work order to delivery of the finished product.
Question 6: Forward scheduling is best suited for situations where:
- Due dates are fixed and cannot change
- Material is available immediately and the earliest completion date is needed (Correct answer)
- Inventory must be minimized
- Machine capacity is unlimited
Correct answer: Material is available immediately and the earliest completion date is needed
Forward scheduling starts from the current date and schedules operations forward to find the earliest possible completion date.