CPT Production Planning & Scheduling Flashcards

6 cards from real CPT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 CPT Production Planning & Scheduling flashcards as text
  1. What does MRP stand for in a manufacturing context?

    Answer: Material Requirements Planning

    MRP stands for Material Requirements Planning, a system used to calculate material needs based on production schedules.

  2. Which scheduling method schedules jobs by starting from the due date and working backwards?

    Answer: Backward scheduling

    Backward scheduling starts from the required due date and works back to determine when each operation must begin.

  3. What is a production schedule's primary purpose?

    Answer: Coordinate material, labor, and equipment to meet delivery commitments

    A production schedule coordinates resources—people, materials, and machines—so orders are completed on time.

  4. What does 'cycle time' mean in production scheduling?

    Answer: Time between the start of successive units

    Cycle time is the elapsed time between completing one unit and the next unit of the same product.

  5. A work order that lists every operation, machine, and sequence needed to produce a part is called a:

    Answer: Route sheet

    A route sheet (or routing) documents each manufacturing step, the machine or workstation required, and the sequence of operations.

  6. What is the purpose of a capacity requirements plan (CRP)?

    Answer: Verify that available machine and labor hours can handle the planned workload

    CRP compares the production workload against available capacity to identify bottlenecks before they cause delays.