CPT Production Planning & Scheduling Flashcards
6 cards from real CPT practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 CPT Production Planning & Scheduling flashcards as text
What is a 'bottleneck' in a production process?
Answer: The operation that limits overall throughput
A bottleneck is the slowest operation in a process; it constrains the output rate of the entire production line.
Which term describes the planned quantity of product to be produced in a specific time period?
Answer: Production quota
A production quota is the target output quantity assigned for a given shift, day, or week.
Takt time is calculated by dividing:
Answer: Available production time by customer demand rate
Takt time = available production time รท customer demand; it sets the pace at which products must be completed.
Which document communicates the quantity of a product to be built and its due date to the shop floor?
Answer: Work order / job ticket
A work order (job ticket) authorizes production of a specific quantity by a specific date and travels with the job on the floor.
What is 'lead time' in a manufacturing environment?
Answer: The total time from order release to completion of a part or product
Lead time is the total elapsed time required to produce an item, from the release of a work order to delivery of the finished product.
Forward scheduling is best suited for situations where:
Answer: Material is available immediately and the earliest completion date is needed
Forward scheduling starts from the current date and schedules operations forward to find the earliest possible completion date.