CPSM CSPM Time, Cost & Resource Management 4 — Questions and Answers
Question 1: Which type of project cost is directly tied to the amount of work performed, such as hourly labor costs?
- Fixed costs
- Variable costs (Correct answer)
- Sunk costs
- Indirect costs
Correct answer: Variable costs
Variable costs change in proportion to the work performed, such as labor charged by the hour.
Question 2: A project manager wants to shorten the schedule by adding resources to critical path tasks. This technique is called:
- Fast tracking
- Crashing (Correct answer)
- Resource smoothing
- Schedule compression baseline
Correct answer: Crashing
Crashing adds resources (people, equipment, overtime) to critical path tasks to shorten duration, typically at increased cost.
Question 3: What term describes the costs already spent on a project that cannot be recovered regardless of future decisions?
- Opportunity costs
- Variable costs
- Sunk costs (Correct answer)
- Indirect costs
Correct answer: Sunk costs
Sunk costs are past expenditures that are irrelevant to future decision-making because they cannot be recovered.
Question 4: A Responsibility Assignment Matrix (RAM) maps project roles to work packages. What does a RACI chart specifically track?
- Risk, Assumption, Constraint, Issue for each task
- Responsible, Accountable, Consulted, Informed for each task (Correct answer)
- Resources, Activities, Costs, Inputs for each deliverable
- Roles, Authorities, Commitments, Interfaces for team members
Correct answer: Responsible, Accountable, Consulted, Informed for each task
A RACI chart clarifies who is Responsible, Accountable, Consulted, and Informed for each project task or deliverable.
Question 5: What is the primary difference between 'free float' and 'total float' in schedule management?
- Free float is the delay allowed before impacting a successor; total float is the delay allowed before impacting the project end (Correct answer)
- Free float applies to the whole project; total float applies to individual tasks
- Free float is used in critical chain; total float is used in CPM
- Free float includes resource constraints; total float does not
Correct answer: Free float is the delay allowed before impacting a successor; total float is the delay allowed before impacting the project end
Free float is how long a task can be delayed without delaying its immediate successor, while total float is how long it can be delayed without delaying the project end date.
Question 6: A project manager calculates a To-Complete Performance Index (TCPI) greater than 1.2. What does this suggest?
- The project is performing well and will finish under budget
- The required future cost efficiency is unrealistically high, indicating the budget may need revision (Correct answer)
- The project has surplus funds and can add scope
- The project will finish ahead of schedule
Correct answer: The required future cost efficiency is unrealistically high, indicating the budget may need revision
A TCPI above 1.2 means remaining work must be completed at a significantly higher efficiency than historical performance, signaling the need to revisit the budget.
Question 7: Which scheduling method determines the longest path through the project network to identify the minimum project duration?
- Program Evaluation and Review Technique (PERT)
- Critical Path Method (CPM) (Correct answer)
- Critical Chain Method (CCM)
- Precedence Diagramming Method (PDM)
Correct answer: Critical Path Method (CPM)
The Critical Path Method (CPM) identifies the longest sequence of dependent activities, which determines the shortest possible project completion time.
Which type of project cost is directly tied to the amount of work performed, such as hourly labor costs?