← All CPSM Flashcard Decks

CSPM Time, Cost & Resource Management Flashcards

7 cards from real CPSM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 CSPM Time, Cost & Resource Management flashcards as text
  1. A project's Cost Variance (CV) is -$20,000 and its Earned Value (EV) is $80,000. What is the Actual Cost (AC)?

    Answer: $100,000

    CV = EV – AC, so AC = EV – CV = $80,000 – (–$20,000) = $100,000.

  2. What scheduling technique splits a task and allows another higher-priority task to use the resource temporarily?

    Answer: Preemptive scheduling

    Preemptive scheduling interrupts a lower-priority task so a higher-priority task can use the shared resource.

  3. Which document formally authorizes a project and provides the project manager with authority to apply organizational resources?

    Answer: Project charter

    The project charter formally authorizes the project and grants the project manager authority to allocate resources.

  4. A schedule compression technique that overlaps phases or tasks that would normally be done sequentially is called:

    Answer: Fast tracking

    Fast tracking overlaps sequential activities to shorten the project schedule, often increasing risk.

  5. In the critical chain method, what is a 'project buffer' used for?

    Answer: Protecting the project end date from accumulated uncertainties

    A project buffer in the critical chain method absorbs uncertainty from all tasks on the critical chain to protect the final project due date.

  6. When should a project manager use analogous cost estimating?

    Answer: Early in the project when limited information is available

    Analogous estimating uses data from similar past projects and is most useful early on when detailed information is scarce.

  7. A project is 50% complete with a BAC of $200,000, EV of $80,000, and AC of $100,000. What is the CPI?

    Answer: 0.80

    CPI = EV / AC = $80,000 / $100,000 = 0.80, meaning the project is getting only 80 cents of value for every dollar spent.