A park agency discovers mid-project that grant expenditures will exceed the budgeted amount in one line item. What is the FIRST action the project director should take?
-
A
Spend from the general fund and reimburse it at project close
-
B
Review the grant agreement for budget modification policies and contact the program officer
-
C
Reduce services to stay within the original budget without notifying the funder
-
D
Transfer funds from the indirect cost pool without documentation