A park agency is preparing its five-year CIP and needs to balance immediate community demands with long-term infrastructure needs. Which tool best supports this balancing act?
-
A
A scoring matrix that weighs both short-term need and long-term strategic alignment
-
B
A random lottery system for project selection
-
C
Exclusive focus on projects with the highest revenue potential
-
D
Approval of all projects submitted by park staff without prioritization