A construction contract includes a clause that requires the contractor to pay the public agency a predetermined amount of $1,000 for each day that completion is late. This contract clause is best described as:
-
A
A punitive penalty
-
B
An insurance bond
-
C
A liquidated damages clause
-
D
An advance payment recovery