A packaging engineer uses a Failure Mode and Effects Analysis (FMEA). What does the Risk Priority Number (RPN) represent?
-
A
Sum of severity, occurrence, and detectability scores
-
B
Product of severity, occurrence, and detectability scores
-
C
Ratio of severity to detectability
-
D
Weighted average of all risk factors