A supplier submits a Request for Equitable Adjustment (REA) claiming additional costs due to a buyer-directed change. Under the Changes clause, the buyer is MOST responsible for:
-
A
Rejecting all REAs that exceed the original contract value
-
B
Negotiating fair compensation for costs directly caused by the directed change
-
C
Requiring the supplier to absorb all additional costs as part of normal risk
-
D
Issuing a new contract for any work outside the original scope