A CPP must negotiate material lead times with a primary packaging supplier. Which negotiation tactic is MOST aligned with a long-term partnership approach?
-
A
Demand the shortest possible lead times regardless of supplier capacity
-
B
Share demand forecasts and collaborate on planning to achieve mutually beneficial lead times
-
C
Switch suppliers immediately if any delay occurs
-
D
Avoid disclosing internal project timelines