  1. A buyer orders a change within the general scope of the contract under a changes clause. What is the supplier normally entitled to?

    Answer: An equitable adjustment in price and/or schedule

    Changes clauses let the buyer modify the scope unilaterally, while the supplier is entitled to an equitable adjustment for the cost or schedule impact.

  2. A buyer ends a contract because it no longer needs the goods, not because the supplier failed. This is called termination for:

    Answer: Convenience

    Termination for convenience lets the buyer end the contract without supplier fault, normally paying for work performed plus reasonable settlement costs.

  3. Before terminating a contract for default, a buyer typically issues a notice giving the supplier a set period to correct the problem. This notice is a:

    Answer: Cure notice

    A cure notice tells the supplier about the deficiency and gives a set time (often 10 days) to remedy it before default termination.

  4. An engineer who lacks contracting authority tells a supplier to add features not in the contract, and the supplier complies. This situation is best described as:

    Answer: A constructive change

    A constructive change occurs when informal direction or conduct effectively changes the contract without a formal modification.

  5. Which dispute resolution method uses a neutral third party who helps the parties reach agreement but cannot impose a binding decision?

    Answer: Mediation

    A mediator helps the parties negotiate a settlement but, unlike an arbitrator or judge, cannot impose a decision.

  6. Transferring a contract to a new party so that the new party fully replaces the original and releases it from obligations requires:

    Answer: A novation agreement with consent of all parties

    A novation substitutes a new party for an original one and requires consent from all parties, which releases the original party.

  7. What is the primary purpose of a contract closeout process?

    Answer: To verify all obligations are fulfilled, settle final payments and claims, and archive records