  1. According to Juran's Quality Trilogy, the three universal processes of managing quality are:

    Answer: Quality Planning, Quality Control, Quality Improvement

    Juran's Quality Trilogy consists of Quality Planning (designing processes to meet goals), Quality Control (monitoring performance), and Quality Improvement (raising performance to new levels).

  2. A process team calculates that 80% of defects come from 20% of the causes. This observation exemplifies:

    Answer: Pareto's 80/20 rule

    Pareto's 80/20 rule (Pareto Principle) states that roughly 80% of effects come from 20% of causes, guiding teams to focus on the vital few causes.

  3. When calculating Overall Equipment Effectiveness (OEE), which three factors are multiplied together?

    Answer: Availability, Performance, Quality

    OEE = Availability × Performance × Quality, measuring how effectively manufacturing equipment is utilized relative to its full potential.

  4. A process improvement team wants to verify that their corrective action actually eliminated the root cause. The best approach is to:

    Answer: Monitor post-implementation performance data against baseline

    Comparing post-implementation performance data to the pre-improvement baseline provides objective evidence that the root cause was eliminated.

  5. In Lean quality management, 'poka-yoke' refers to:

    Answer: Error-proofing mechanisms that prevent defects from occurring

    Poka-yoke (mistake-proofing) uses design features or mechanisms that prevent errors from being made or make errors immediately obvious when they occur.

  6. A quality manager finds that the upper control limit (UCL) on a control chart is regularly exceeded. The appropriate first action is to:

    Answer: Investigate and identify the assignable cause

    A point outside control limits signals a special cause, which must be investigated and identified before any corrective action can be taken.

  7. Which metric best captures the end-to-end quality performance of a multi-step process with steps having individual yields of 95%, 90%, and 98%?

    Answer: Rolled Throughput Yield (RTY) of 83.8%

    RTY = 0.95 × 0.90 × 0.98 = 0.838 (83.8%), capturing the compounding effect of defects across all process steps.