CPM Project Quality Management 2 — Questions and Answers
Question 1: Which quality control tool is used to determine whether a process is stable and operating within predictable limits over time?
- Pareto chart
- Control chart (Correct answer)
- Cause-and-effect diagram
- Histogram
Correct answer: Control chart
Control charts display process data over time against upper and lower control limits to determine if a process is stable and statistically predictable.
Question 2: A cause-and-effect diagram (Ishikawa/fishbone diagram) is primarily used to:
- Track defect frequency over time
- Identify potential root causes of a problem (Correct answer)
- Monitor process control limits
- Measure customer satisfaction levels
Correct answer: Identify potential root causes of a problem
The cause-and-effect diagram visually maps potential root causes of a defect or problem, organized by categories such as people, process, materials, and equipment.
Question 3: What is 'statistical sampling' used for in project quality control?
- To eliminate all defects from a deliverable through exhaustive review
- To inspect a representative subset of items rather than the entire population (Correct answer)
- To calculate the project's total cost of quality
- To assign performance ratings to quality team members
Correct answer: To inspect a representative subset of items rather than the entire population
Statistical sampling inspects a representative portion of a population, providing reliable quality data more cost-effectively than 100% inspection.
Question 4: In a quality control chart, what does a 'control limit' represent?
- The maximum budget allowed for quality activities
- The statistical boundary beyond which a process is considered out of control (Correct answer)
- The minimum acceptable performance level agreed with the client
- The target value for all project deliverables
Correct answer: The statistical boundary beyond which a process is considered out of control
Control limits define the expected range of variation for a stable process; data points outside these limits signal potential process instability requiring investigation.
Question 5: During project execution, a quality audit is best described as:
- A financial review of quality-related expenditures
- A structured review to identify gaps between current practices and quality standards (Correct answer)
- A final inspection of deliverables before customer handover
- A survey to gauge customer preferences for product features
Correct answer: A structured review to identify gaps between current practices and quality standards
A quality audit systematically examines whether quality processes are being followed correctly and identifies areas for improvement and compliance.
Question 6: What is the primary purpose of using a 'checklist' as a quality control tool?
- To track the frequency of stakeholder communications
- To ensure consistent completion of all required quality steps (Correct answer)
- To measure individual team member performance
- To document and prioritize project risks
Correct answer: To ensure consistent completion of all required quality steps
Checklists are structured tools that ensure all required quality steps are completed consistently, reducing the likelihood of omissions or errors.
Question 7: When should quality control activities ideally begin in a project?
- Only after all deliverables are fully complete
- During the project planning phase before any work begins
- As work products are being produced throughout the project (Correct answer)
- Only when defects are formally reported by the customer
Correct answer: As work products are being produced throughout the project
Quality control activities should occur throughout the project as work products are produced, enabling early detection and less costly correction of defects.