CPM Project Execution & Delivery 3 — Questions and Answers
Question 1: What is the primary purpose of managing project knowledge during execution?
- To create a lessons learned register at project close
- To leverage existing knowledge and create new knowledge to improve outcomes (Correct answer)
- To document team member competencies for performance reviews
- To maintain a risk register with up-to-date information
Correct answer: To leverage existing knowledge and create new knowledge to improve outcomes
Managing project knowledge uses existing knowledge and creates new knowledge to improve current performance and future projects.
Question 2: Schedule crashing differs from fast tracking in that crashing:
- Overlaps sequential activities to save time
- Adds resources to critical path activities to shorten duration (Correct answer)
- Removes non-critical activities from the schedule
- Reduces the number of quality inspections
Correct answer: Adds resources to critical path activities to shorten duration
Crashing adds resources (cost) to critical path tasks to reduce duration, whereas fast tracking overlaps tasks.
Question 3: A project manager is conducting a team performance assessment. Which factor is LEAST relevant to this assessment?
- Team cohesion and collaboration
- Individual technical skill improvements
- Stakeholder satisfaction scores from external surveys (Correct answer)
- Resolution of interpersonal conflicts
Correct answer: Stakeholder satisfaction scores from external surveys
External stakeholder satisfaction surveys measure project performance, not team development effectiveness.
Question 4: During execution, which conflict resolution technique is considered MOST effective for long-term resolution?
- Smoothing/accommodating
- Forcing
- Collaborating/problem solving (Correct answer)
- Withdrawing/avoiding
Correct answer: Collaborating/problem solving
Collaborating addresses the root cause and finds a win-win solution, making it the most durable conflict resolution approach.
Question 5: When implementing approved changes during project execution, the project manager must ensure:
- The project charter is updated to reflect all changes
- Only the project management plan sections directly affected are updated
- All relevant project documents and plans are updated for consistency (Correct answer)
- The change log replaces the need to update other documents
Correct answer: All relevant project documents and plans are updated for consistency
Approved changes must be reflected across all affected project documents to maintain consistency and integrity.
Question 6: A project manager uses a RACI chart during execution. What does the 'I' stand for?
- Initiator
- Informed (Correct answer)
- Inspector
- Integrated
Correct answer: Informed
In a RACI chart, 'I' stands for Informed — those who are kept up-to-date on progress but do not make decisions.
Question 7: Which of the following best describes the role of the project manager during the execution phase?
- Primarily technical advisor ensuring quality standards are met
- Coordinator of project work while managing stakeholder expectations (Correct answer)
- Sole decision-maker for all project issues and changes
- Administrator focused on documenting completed activities
Correct answer: Coordinator of project work while managing stakeholder expectations
During execution, the PM coordinates team efforts, manages stakeholders, and ensures alignment with the project management plan.
What is the primary purpose of managing project knowledge during execution?