Which project scheduling technique uses three time estimates (optimistic, most likely, pessimistic) to account for uncertainty in activity durations?
-
A
Gantt chart
-
B
Critical Path Method (CPM)
-
C
Program Evaluation and Review Technique (PERT)
-
D
Work Breakdown Structure (WBS)