A project manager discovers that a key deliverable is two weeks behind schedule. Which response best applies the critical path method (CPM) to recover?
-
A
Extend the project deadline by two weeks
-
B
Crash activities on the critical path by adding resources
-
C
Remove non-critical tasks from scope
-
D
Reassign the project to a more experienced manager