A Rough-Cut Capacity Plan (RCCP) differs from Capacity Requirements Planning (CRP) in that RCCP:
-
A
Uses actual shop-floor queue data and routing details
-
B
Checks capacity at only key or critical resources against the MPS, before MRP is run
-
C
Plans capacity all the way to the supplier level
-
D
Replaces the need for a Master Production Schedule