In MRP, what is the purpose of 'time-phasing' requirements?
-
A
To stagger demand across shifts for labor balance
-
B
To offset gross requirements by lead time so orders are placed at the right time
-
C
To phase out obsolete materials from inventory
-
D
To synchronize production with customer shipping windows