When developing a maintenance schedule, 'schedule compliance' is measured as:
-
A
The ratio of emergency work orders to planned work orders
-
B
The percentage of planned work orders completed as scheduled
-
C
The accuracy of estimated versus actual labor hours
-
D
The number of PM tasks completed per technician per week