A manager notices that actual labor costs exceeded the budget by 12% for three consecutive months. Which corrective action addresses the root cause most directly?
-
A
Reduce overtime approval thresholds
-
B
Conduct a variance analysis to identify whether hours or rates drove the overage
-
C
Transfer funds from another budget line
-
D
Request a budget increase for next quarter