MRP & Production Control Flashcards

7 cards from real CPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 MRP & Production Control flashcards as text
  1. What distinguishes a 'net change' MRP run from a 'regenerative' MRP run?

    Answer: Net change recalculates only the items affected by recent transactions, while regenerative re-plans the entire database

    Net change MRP updates only items impacted by changes since the last run, making it faster and more responsive than a full regenerative run.

  2. In capacity requirements planning, 'load' on a work center is calculated as:

    Answer: Sum of setup time plus run time for all planned and released orders scheduled at that work center

    Load is the total setup and run time demand placed on a work center by all planned and released orders, compared to available capacity to identify overloads.

  3. Which statement best describes the role of 'offsetting' in MRP calculations?

    Answer: It moves planned order releases earlier in time by the item's lead time

    Lead-time offsetting shifts the planned order release date earlier by the item's lead time so materials arrive when the gross requirement is due.

  4. A plant manager wants to reduce manufacturing lead time without adding capacity. Which strategy is most directly effective?

    Answer: Reduce queue time by controlling work-in-process levels and releasing fewer orders to the floor

    Queue time typically constitutes 80–90% of manufacturing lead time; controlling WIP through input/output management directly reduces queue and shortens lead time.

  5. In production planning, a 'chase demand' strategy means:

    Answer: Varying production output to match demand fluctuations, adjusting workforce or overtime as needed

    A chase strategy adjusts production rate and workforce up or down to follow actual demand, minimizing inventory at the cost of workforce flexibility.

  6. When MRP creates a 'reschedule-in' exception message, it is recommending that the planner:

    Answer: Move an existing order to an earlier date because requirements have accelerated

    A reschedule-in message tells the planner that an open order's due date should be moved earlier to satisfy a requirement that is needed sooner than originally planned.

  7. Which MRP planning concept uses the idea that items at the same low-level code are netted together before planned orders are exploded to child components?

    Answer: Low-level coding and netting

    Low-level coding ensures all demands for a shared part across all BOM branches are consolidated and netted at its lowest BOM level before child requirements are generated.