Maintenance and Reliability Flashcards

7 cards from real CPM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Maintenance and Reliability flashcards as text
  1. When developing a maintenance schedule, 'schedule compliance' is measured as:

    Answer: The percentage of planned work orders completed as scheduled

    Schedule compliance measures what percentage of planned maintenance work orders are completed within the scheduled period, reflecting planning and execution effectiveness.

  2. A plant experiences repeated seal failures on centrifugal pumps. The maintenance team suspects misalignment. Which alignment method provides the highest precision?

    Answer: Laser shaft alignment

    Laser shaft alignment provides the highest precision and repeatability for aligning rotating machinery, reducing vibration, seal wear, and bearing failures.

  3. A plant manager wants to benchmark maintenance performance against industry peers. Which metric is most commonly used for this comparison?

    Answer: Maintenance cost as a percentage of replacement asset value (RAV)

    Maintenance cost as a percentage of RAV normalizes spending to asset value, making it the most widely used metric for cross-industry maintenance benchmarking.

  4. In the context of spare parts management, 'ABC analysis' is used to:

    Answer: Categorize spare parts by their usage value to optimize inventory investment

    ABC analysis classifies spare parts into A (high-value, low-volume), B (moderate), and C (low-value, high-volume) categories to focus inventory control efforts appropriately.

  5. Which maintenance concept focuses on designing equipment so that it can be easily and quickly restored to operating condition after a failure?

    Answer: Maintainability

    Maintainability is the measure of how easily and quickly a failed system can be restored to its functional state, often expressed as Mean Time To Repair (MTTR).

  6. A plant is evaluating whether to rebuild an aging compressor or replace it. Which economic analysis tool is most appropriate for comparing these alternatives over a multi-year period?

    Answer: Life Cycle Cost (LCC) analysis

    Life Cycle Cost analysis compares total costs of ownership including acquisition, operation, maintenance, and disposal over the equipment's useful life to support replace-or-repair decisions.

  7. During a plant shutdown, a maintenance crew performs work that was identified during routine inspections but deferred until the scheduled outage. This practice is known as:

    Answer: Deferred corrective maintenance

    Deferred corrective maintenance refers to identified repair work that is deliberately postponed and bundled into a planned shutdown to minimize production disruption.