A planner discovers that a supplier's quoted lead time has increased from 4 weeks to 7 weeks. What is the most immediate impact on the supply plan?
-
A
Safety stock can be reduced to compensate
-
B
Planned order release dates must be moved earlier to prevent stockouts
-
C
The reorder point decreases proportionally
-
D
The economic order quantity automatically adjusts upward