Which technique is used to convert a family-level production plan into individual end-item schedules in the MPS?
-
A
Capacity requirements planning (CRP)
-
B
Planning bill of materials (planning BOM)
-
C
Available-to-promise (ATP) logic
-
D
Distribution requirements planning (DRP)