Which planning horizon characteristic best distinguishes a master production schedule (MPS) from a long-range production plan?
-
A
MPS covers years; long-range covers weeks
-
B
MPS is stated in specific end items; long-range uses product families
-
C
MPS is updated annually; long-range is updated weekly
-
D
MPS focuses on capacity; long-range focuses on materials