What is the difference between 'scheduled receipt' and 'planned order receipt' in MRP?
-
A
There is no difference; they are the same
-
B
Scheduled receipts are open orders already released; planned orders are not yet released
-
C
Planned orders are customer orders; scheduled receipts are purchase orders
-
D
Scheduled receipts appear only in the master schedule