What is 'finite capacity scheduling' as opposed to 'infinite capacity scheduling'?
-
A
Finite scheduling enforces actual capacity limits when creating schedules, while infinite scheduling ignores capacity constraints
-
B
Finite scheduling is used only for short-horizon planning
-
C
Infinite scheduling is more accurate because it uses real-time data
-
D
Finite scheduling requires more detailed BOM data than infinite scheduling