  1. Which capacity planning technique evaluates capacity needs at the work-center level using planned and released orders?

    Answer: Capacity Requirements Planning (CRP)

    CRP uses MRP output (planned and released orders) to calculate detailed capacity loads at each work center.

  2. In capacity planning, what does 'demonstrated capacity' represent?

    Answer: Actual capacity achieved based on historical output data

    Demonstrated capacity is the historical average of actual output achieved, reflecting real-world performance rather than theoretical maximums.

  3. A company has a planned load of 480 standard hours and a demonstrated capacity of 400 hours per week. What is the load percentage?

    Answer: 120%

    Load % = (Planned Load / Capacity) × 100 = (480 / 400) × 100 = 120%, indicating the work center is overloaded.

  4. Which of the following is a technique to manage capacity overloads identified in CRP?

    Answer: Overtime, subcontracting, or rescheduling orders

    Common responses to overloads include authorizing overtime, subcontracting work, splitting lots, or rescheduling orders to under-loaded periods.

  5. What is 'queue time' as used in capacity and scheduling planning?

    Answer: Time a job spends waiting before it is processed at a work center

    Queue time is the waiting time that a job spends at a work center before actual processing begins, often the largest component of total lead time.

  6. Which input is NOT typically used in Capacity Requirements Planning (CRP)?

    Answer: Customer satisfaction scores

    CRP relies on MRP output, work center capacity data, and routing information — customer satisfaction scores are not an input.