In site planning for erosion control, what is the primary purpose of establishing a 'construction limit of disturbance' (LOD) line on the plan?
-
A
To define the boundary of the surveyed property
-
B
To clearly delineate where land disturbance activities are permitted to occur
-
C
To mark the edge of the required buffer zones from streams
-
D
To indicate where final grading will match existing grade