A construction site operator wants to terminate coverage under an NPDES Construction General Permit. Which condition must be met before a Notice of Termination (NOT) can be submitted?
-
A
All BMPs must be inspected one final time
-
B
Final stabilization has been achieved and any temporary BMPs have been removed
-
C
The project owner has sold the property to a new owner
-
D
The local municipality has issued a certificate of occupancy