A state environmental agency issues a 'compliance schedule' as part of an enforcement action. This legal instrument requires the violator to:
-
A
Immediately shut down the construction project
-
B
Achieve full compliance through a series of specified steps within defined deadlines
-
C
Pay a penalty and resume normal operations
-
D
Transfer the permit to a third-party environmental manager