A SWPPP must be developed and implemented before land disturbance begins on a project exceeding one acre. Who is legally responsible for certifying the SWPPP?
-
A
The licensed professional engineer who designed the erosion controls
-
B
The permitted operator or an authorized representative
-
C
The state environmental agency reviewer
-
D
The local municipality's stormwater coordinator