CPE Risk Management & Quality Assurance 2 — Questions and Answers
Question 1: Which risk response strategy involves shifting the negative impact of a risk to a third party, such as through insurance?
- Avoid
- Mitigate
- Transfer (Correct answer)
- Accept
Correct answer: Transfer
Risk transfer moves the financial or operational impact of a risk to another party, typically via insurance or contractual agreements.
Question 2: In Monte Carlo simulation for schedule risk analysis, what does the P80 value represent?
- The most likely completion date
- The date with an 80% probability of being met or exceeded (Correct answer)
- The date with an 80% probability of being missed
- The average of 80 simulation runs
Correct answer: The date with an 80% probability of being met or exceeded
P80 means there is an 80% probability that the project will complete on or before that date based on the simulation results.
Question 3: A Fishbone (Ishikawa) diagram is primarily used in quality management to:
- Track defect frequency over time
- Identify root causes of quality problems (Correct answer)
- Rank defects by financial impact
- Establish control limits for processes
Correct answer: Identify root causes of quality problems
A Fishbone diagram helps teams systematically explore all potential root causes of a quality issue by categorizing contributing factors.
Question 4: Which of the following best describes a 'Risk Breakdown Structure' (RBS)?
- A list of all identified risks sorted by priority
- A hierarchical framework categorizing sources of project risk (Correct answer)
- A Gantt chart showing risk response timelines
- A budget allocation tool for risk reserves
Correct answer: A hierarchical framework categorizing sources of project risk
An RBS organizes risks into hierarchical categories (technical, external, organizational, etc.) to ensure comprehensive risk identification.
Question 5: What is the primary purpose of a quality audit in a construction planning project?
- To approve project deliverables for final payment
- To independently assess whether quality processes are being followed (Correct answer)
- To reassign responsibilities after a defect is found
- To calculate the cost of rework needed
Correct answer: To independently assess whether quality processes are being followed
Quality audits verify that defined quality management processes and standards are being implemented correctly on the project.
Question 6: When performing qualitative risk analysis, a risk with HIGH probability and HIGH impact should be placed in which quadrant of a probability-impact matrix?
- Low priority / monitor only
- Medium priority / contingency plan
- High priority / immediate action required (Correct answer)
- Out of scope / escalate to sponsor
Correct answer: High priority / immediate action required
High probability combined with high impact places a risk in the top-priority quadrant requiring active risk response planning.
Question 7: In project risk management, what is the difference between 'residual risk' and 'secondary risk'?
- Residual risk is larger; secondary risk is smaller
- Residual risk remains after response; secondary risk arises from the response itself (Correct answer)
- Residual risk is unidentified; secondary risk is known
- They are the same concept with different names
Correct answer: Residual risk remains after response; secondary risk arises from the response itself
Residual risks are what remains after mitigation actions, while secondary risks are new risks introduced by implementing the risk response.
Which risk response strategy involves shifting the negative impact of a risk to a third party, such as through insurance?