An estimator is pricing lumber for a project starting in 9 months. Which approach best accounts for price volatility?
-
A
Apply a historical escalation rate and add a contingency allowance
-
B
Use today's spot price with no adjustment
-
C
Base the estimate on the lowest quote received
-
D
Use the average of the last 5 years' prices without adjustment